Main stages

 A clear and logically structured schedule guides the sequence of tasks: first year of the project is dedicated to design and specific studies of both infrastructure and vehicle that will be built during the second year. Demonstration will take place during the third and final year of the project that includes exploitation of monitoring data, of users’ feedback and of technological breakthroughs.

The project is a challenge in terms of planning as both infrastructure and vehicle definition, design and manufacturing are running in parallel over the whole project duration.

NEWS BOX

The 6th MobyPost Newsletter is available
MobyPost's 6th Newletter edition is now released. This last newsletter includes interesting information about MobyPost testing phase, the new UTBM campus and other news from the hydrogen field.

more news...

COUNTER FOR RENEWABLE
HYDROGEN PRODUCTION
kg
17

(last update: November 18, 2015)
Vehicle
  • Definition of system requirements
  • Simulation and modelling studies of powertrain
  • Style and ergonomic studies
  • Mechanical Engineering

Infrastructure
  • Definition of system requirements
  • Dimensioning of equipment
  • Safety and regulation analysis
  • Design of monitoring system
Vehicle
  • Final design and test of powertrain
  • Construction of vehicles
  • Homologation

Infrastructure
  • Photovoltaic generator installation
  • Modification work on existing buildings
  • Installation of electrolyser, H2 storage,
    H2 refuelling station
  • Certification
  • Training for postmen
  • Field tests
  • Data analysis
  • Dissemination
     & knowledge transfer